It’s not just the issue of security that is at stake in overly depending on Chinese equipment for our power transmission and generation needs. There are serious issues over the quality of the material too.


A television debate following the simultaneous failure of three grids on July 31 revealed India’s plans to integrate its power grid with China, and other neighbours. Not being a subject expert, one cannot opine if this conflicts with current moves by States to ensure ‘islanding’, so that sudden fluctuations in drawing power from the grid do not trigger total blackouts across states. Experts, however, point out that just as the dominance of foreign direct investment in the telecommunications sector is a permanent threat to national security, (and in the aviation sector in times of war), so also a critical sector like power should not be dominated by a nation with territorial claims on India.

One reason for the collapse of the northern, eastern, and north-eastern grids last month is inadequate power generation and obsolete, ill-maintained infrastructure. Now, as India gears up to meet the estimated increase in demand (an additional 3,15,000 MW by 2017; investment $600 billion) to support the desired eight per cent growth rate, doubts are surfacing over the service, operations and maintenance, and longevity of Chinese power equipment that is steadily dominating India’s power sector.

According to official figures, in the 11th Plan period (2007-12), the total capacity added stood at 45,064 MW, of which Chinese equipment accounted for 17,772 MW (market share 39.4 per cent). Of the 2012-onwards under-construction capacity of 96,650 MW of thermal power, Chinese equipment account for 38,900 MW (market share 40.2 per cent), leaving the balance of 57,750 MW to BHEL and joint ventures which will import equipment — mainly boilers, turbines and generators — from established multinational partners and eventually reduce the market share of Chinese power firms. The Government’s recent decision to impose duty at peak rates (21 per cent) may also affect future imports from Chinese firms. Hitherto, supplies to all domestic power projects above 1000 MW capacity invited zero per cent customs duty.
As of now, the high market share of Chinese power equipment is mainly because Independent Power Producers  and other clients find these 20-25 per cent cheaper than domestically manufactured equipment. It is also delivered on time, averting delays and cost overruns; a delay of six-12 months increases costs by roughly 10 per cent. Above all, the deals are sweetened by easy financing.

A Forbes study noted that Indian regulations require power generation firms to have a debt equity ratio of 30:70. A company planning to expand capacity by thousands of megawatts over the next few years would have problems raising so much capital at high interest rates (Indian banks usually charge 10-13 per cent). Chinese banks levy just four-to-six per cent, but this also involves purchasing equipment from Chinese firms, a strategy that has enabled Shanghai Electric and Dongfang Electric to bag orders to the tune of 40,000 MW from private players.

China has also made rapid inroads in the local transformer market, putting established giants like Bharat Heavy Electricals Ltd and others on the defensive. Recently, the Power Grid Corporation of India gave Chinese firms 46 per cent of its orders for high-grade 765 kV transformers needed to support 765 kV transmission lines which transport power from super critical power plants with generation capacity of 660 MW and above.

The flip side is that serious problems have cropped up with Chinese equipment at many places. The Haryana Power Generation Corporation’s Yamuna Nagar thermal power station had to shut down both its 300 MW units since April 2012, as also two 600 MW units at Khedar, Hissar (one was fixed later), causing a shortage of 1000 MW at the height of the paddy season.
At Yamuna Nagar — Haryana’s first plant awarded to the private sector — both turbines failed within just four years of commissioning. Last year, one turbine rotor failed and was sent to Siemens’ Baroda workshop for repair, at a cost of five crore rupees.

An enquiry by the Haryana Power Generation Corporation Ltd identified two major lapses in design/construction, but the firm that set up the plant is unwilling to accept or admit the lapses and has refrained from rectification work.

At Khedar, the turbine blades were damaged as a ‘sealing strip’ inside the turbine came loose and dented the blades. In the absence of a service facility in India, the turbine had to be shipped to Shanghai Electric Co’s facility in China for repairs. Official sources say Haryana purchased the Chinese equipment at Rs3.49 crore per MW at Yamuna Nagar, and Rs3.19 crore per MW at Khedar; similar BHEL units would have cost Rs4 to Rs4.5 crore per MW. But now, the apparent gains have been wiped out by poor performance and generation loss.

Other plants with problems include West Bengal Power Development Corporation Ltd’s Sagardighi Thermal Power Plant, where the turbine blades collapsed and the piping systems in the boiler had snags; and the Durgapur Thermal Power Project.

Obviously, the O&M costs of Chinese equipment vis-à-vis domestic companies with manufacturing and in-situ service facilities are higher. Hence, given their massive footprint in the Indian power sector, Chinese firms are moving to set up manufacturing facilities in India to service clients, supply spare parts and overhaul power plants.

Meanwhile, public sector BHEL , which has been on the back foot since the Chinese inroads, claims that its power equipment is more efficient, reliable, and suited for the mixed coal used in India; also, its plants consume less fuel than those of the competition. This is supported by a Bank of America-Merrill Lynch report which says that BHEL equipment is superior to Chinese products after accounting for parameters such as auxiliary consumption, heat rate, plant load factor and metallurgy.

Auxiliary consumption is the energy used by auxiliaries like cooling towers, while heat rate measures the ability of a machine to convert heat into power. Plant load factor is the ability of a plant to perform to its rated capacity. These overcome the lower costs of Chinese plants in the long run.

BHEL’s core problem is low capacity which causes huge delivery delays and commensurate cost escalation for clients. But now, pushed into a corner by Chinese commercial aggression, it is planning a subsidiary to finance power projects from its Rs10,000 crore cash surplus.

Supplemented by tax-free bonds up to Rs2 lakh per citizen, and interest-free bonds for money returned from foreign havens, we could finance all our infrastructure needs domestically. India does not lack resources, but needs will- power and wisdom to marshal them effectively.